Not recommended. This work requires licensed professionals due to inherent safety risks (gas leaks, explosions), complex code requirements across multiple disciplines (gas fitting, electrical), and specialized equipment.
This project involves specialized gas fitting and electrical work, strict adherence to national and local codes, coordination with utility providers, and specific climate considerations such as DuPage County's 42-inch frost depth. Improper execution carries significant safety risks.
Project Guidelines & Rules
Permitting and Planning
3 Rules
Obtain all necessary permits from your local municipality prior to commencing any work. Plans detailing the existing and proposed meter location, gas line routing, and electrical bonding points must be submitted.
2024 IRC R105.1, R106.1
Coordinate extensively with the local gas utility company for service disconnection, relocation, and reconnection. This is a critical first step and often dictates project timelines.
Utility-specific requirement; implied by 2024 IRC for safe modification of gas systems.
Ensure all work is performed by properly licensed and insured contractors. Gas piping and appliance work requires a licensed plumber or gas fitter. Electrical work requires a licensed electrician.
Illinois Plumbing Code (general licensing requirement), 2023 NEC 90.1(B)
Gas Piping Installation (IRC & Illinois Plumbing Code)
5 Rules
New and relocated gas piping must be sized correctly based on the longest run, pressure drop, and total BTUH load of all connected appliances to ensure adequate gas supply.
2024 IRC G2413 (402.1), Illinois Plumbing Code 890.1340
All new and relocated gas piping must be tested for leaks after installation and before concealment, witnessed by the inspector.
2024 IRC G2417 (406), Illinois Plumbing Code 890.1350
Approved piping materials and joint connections must be utilized. Plastic pipe is not permitted above ground or inside buildings.
2024 IRC G2414 (403), Illinois Plumbing Code 890.1330
Underground gas piping must be installed with a minimum 12-inch cover. Deeper burial may be required based on local soil conditions or other utility crossings.
2024 IRC G2415.5 (404.5)
Proper clearances from other utilities, structural elements, and penetrations must be maintained. All piping must be adequately supported.
2024 IRC G2415 (404.1, 404.6)
Gas Meter Location and Protection (IRC)
4 Rules
Gas meters shall be located in an approved, readily accessible position for reading, inspection, and servicing. Consult with the local gas utility for specific placement requirements.
2024 IRC G2416.1 (405.1)
Maintain required clearances from building openings (windows, doors), electrical equipment, ignition sources, and areas prone to vehicle traffic. Typically, 3 feet from openings and 5 feet from electrical panels/meters.
2024 IRC G2416.2 (405.2)
Meters must be adequately protected from physical damage, especially in areas susceptible to vehicular impact. Bollards or other protective barriers may be required.
2024 IRC G2416.2 (405.2)
In DuPage County, where the ground is subject to frost heave, the meter support structure or foundation must extend a minimum of 42 inches below grade or be mounted on a structurally sound, frost-protected building wall.
2024 IRC R403.1 (Frost Protection), DuPage County regional standard (42-inch frost depth)
Electrical Grounding and Bonding (NEC)
3 Rules
The metallic gas piping system, on the customer side of the meter, must be effectively bonded to the building's grounding electrode system.
2023 NEC 250.104(B)
The bonding conductor must be sized according to NEC 250.122 based on the service conductor size, generally no smaller than 6 AWG copper for typical residential services.
2023 NEC 250.104(B), 250.122
Ensure that the bonding connection is made in an accessible location for inspection and maintenance.
2023 NEC 250.104(B) (implied accessible connection)
Excavation and Site Work (IRC)
2 Rules
Any new foundations or support structures for the gas meter must extend to a minimum depth of 42 inches below grade to mitigate frost heave prevalent in DuPage County.
2024 IRC R403.1 (Frost Protection), DuPage County regional standard (42-inch frost depth)
Proper backfill and compaction are required around buried piping and foundations to prevent future settlement and damage.
2024 IRC R403.1.6 (Backfill)
Inspections and Finalization
3 Rules
Schedule and pass all required inspections with your local building department, including rough-in gas piping inspection, pressure test verification, and final inspection.
2024 IRC R109.1, G2417.1 (406.1)
No piping or related components shall be concealed until the rough-in inspection has been approved.
2024 IRC R109.1.2
Ensure all deficiencies noted during inspections are corrected promptly prior to final approval and gas service re-activation.
2024 IRC R109.2